Project #: 4000-23
Issued by: City of Beaverton, OR
Publish Date: Apr 6, 2023 2:00PM
Bids Due Date: Apr 27, 2023 2:00PM (Pacific Daylight Time) add to calendar
Status: awardpending
Award Notes: Notice of Intent to Award to R & R General Contractor's at the June 6, 2023, City Council Meeting. Posted 04/27/23.
Posted: Apr 6, 2023

Description

The City of Beaverton is accepting will only accept electronic bids for the project, Construction of ADA Curb Ramp Retrofit Upgrade Project, Project No. 4000-23 It is the City’s intent to enter into a one-year contract, with the option to renew for an additional one-year term; the total term will not exceed two years. Year one project consists of removal of 2,375 feet of curb, removal of 1,191.3 square yards of walk and driveways, 505 square yards of 4” asphalt pavement repairs approximately requiring 96 tons of asphalt, placing 2,375 feet of curb and gutter, placing 10,026 square feet of monolithic curb and sidewalk and approximately 110 tons of aggregate. The project cost is approximately between $900,000.00 and $1,000,000.00. Year two project consists of 1777 feet of curb, removal of 1,285 square yards of walk and driveways, 439 square yards of 4” asphalt pavement repairs approximately requiring 84 tons of asphalt, placing 1,383 feet of curb and gutter, placing 13,412 square feet of monolithic curb and sidewalk and approximately 132 tons of aggregate. The project cost is approximately between $900,000.00 and $1,000,000.00. Both projects are on-site design-build with no plans for ADA curb ramps design.



Line Items

This solicitation has the following line items for which you can submit a bid. Please review the bidding instructions in the bid documents for information on these line items:

Item No Item Unit of Measure Quantity Required?
BID SCHEDULE A
 
TEMPORARY FEATURES AND APPURTENANCES
1 Mobilization LS 1.00 Required
2 Temp. Work Zone Traffic Control, Complete LS 1.00 Required
3 Erosion Control LS 1.00 Required
4 Inlet Protection EA 35.00 Required
5 Pollution Control Plan LS 1.00 Required
 
ROADWORK
6 Removal of Curb FT 2375.00 Required
7 Removal of Walks & Driveways SY 1191.30 Required
8 Asphalt Pavement Saw Cutting FT 2489.00 Required
9 Clearing and Grubbing LS 1.00 Required
 
DRAINAGE AND SEWERS
10 3 Inch, PVC Pipe, (Weep Holes) FT 46.00 Required
 
WEARING SURFACES
11 4 Inch Asphalt Concrete Pavement Repairs SY 505.30 Required
12 Concrete Curb, Curb and Gutter FT 2375.00 Required
13 Monolithic Curb and Sidewalk SF 10025.50 Required
14 Truncated Dome on New Surface SF 1180.00 Required
 
PERMANENT TRAFFIC CONTROL AND ILLUMINATIN SYSTEM
15 Remove and Reinstall Existing Signs LS 1.00 Required
 
RIGHT OF WAY DEVELOPMENT AND CONTROL
16 Single Mailbox Support EA 6.00 Required
17 Reinstall USPS Cluster Mailbox EA 2.00 Required
 
WATER SUPPY SYSTEM
18 Relocate Irrigation System LS 1.00 Required
 
 
 
BID SCHDULE B
 
TEMPORARY FEATURES AND APPURTENANCES
1 Mobilization LS 1.00 Required
2 Temp. Work Zone Traffic Control, Complete LS 1.00 Required
3 Erosion Control LS 1.00 Required
4 Inlet Protection EA 18.00 Required
5 Pollution Control Plan LS 1.00 Required
 
ROADWORK
6 Removal of Curb FT 1777.00 Required
7 Removal of Walks and Driveways SY 1285.40 Required
8 Asphalt Pavement Saw Cutting FT 2164.50 Required
9 Clearing and Grubbing LS 1.00 Required
 
DRAINAGE AND SEWERS
10 3 Inch, PVC Pipe, (Weep Holes) FT 8.00 Required
 
WEARING SURFACES
11 4 Inch Asphalt Concrete Pavement Repairs SY 439.20 Required
12 Concrete Curb, Curb FT 82.50 Required
13 Concrete Curb, Curb and Gutter FT 1383.20 Required
14 Monolithic Curb and Sidewalk SF 13412.20 Required
15 Truncated Dome on New Surface SF 786.00 Required
 
PERMANENT TRAFFIC CONTROL AND ILLUMINATIN SYSTEM
16 Remove and Reinstall Existing Signs LS 1.00 Required
 
RIGHT OF WAY DEVELOPMENT AND CONTROL
17 Single Mailbox Support EA 1.00 Required
18 Reinstall USPS Cluster Mailbox EA 1.00 Required
 
WATER SUPPY SYSTEM
19 Relocate Irrigation System LS 1.00 Required

Download Line Items as .CSV

Pre-Bid Conference

A Non-Mandatory pre-bid conference for this project will be held by conference call using Zoom on 4/18/2023 at 10:00 AM.

https://www.zoomgov.com/my/beavertonprocurement

Pre-Bid Conference Date Apr 18, 2023 10:00AM (Pacific Daylight Time) add to calendar

Vendor Questions and Answers

Submitted Questions about this Bid

These are questions submitted by vendors for which the agency has supplied an answer.

Questions
Special Section 00120.40 (i): the Substantial Completion date for the FY24/25 is June 30, 2024. Please advise if this is correct.
Asked on 4/13/2023 1:28:52 PM
Answer:

This has been corrected on the main bid document to state that: 

FY 24/25 ADA Curb Ramp Retrofit

1. Notice to Proceed will be issued on July 1, 2024

2. Substantial Completion date is June 30, 2025

 

In the GFE Program: Divisions of Work section it states that "Divisions of work 91430 Concrete Work must be Self-Performed in full by the bidder (Prime Contractor)" Yet it is checked in the NIGP Codes/Work Description section for 91430 Concrete Work. These are contradicting statements in that it must be self-performed in full by the bidder but you must also perform outreach for this scope of work. This would give a false bidding opportunity for our COBID firms. Please advise on how the City plans to revise or enforce this contradiction.
Asked on 4/18/2023 1:23:14 PM
Answer:

On page 13 of the contract “Good Faith Effort Program” under Per-bid Requirements in states

 

Contact Requirements. The City has identified Divisions of Work (“DOW”) or areas where the City has determined that subcontracting opportunities may exist for each of its projects valued over $100,000. If the City has identified DOW, Bidders must make a GFE to contract with a COBID-certified subcontractors for each DOW identified in the solicitation document except for Division of Work “Concrete Work”. NIGP 91430, Concrete Work, must be self-performed in full by the bidder (Prime Contractor).

 

a. A bidder may not use a subcontractor to perform any DOW unless the bidder has made a GFE as required by these requirements.

 

b. A bidder is not required to contact COBID-certified subcontractors for any DOW that will be performed by the bidder. If the bidder indicates that it will Self-Perform work for a particular DOW, except for NIGP 91430 which must be self-performed in full, it may still add a subcontractor in that DOW as long as bidder submits the required documentation as provided in the Subcontractor changes section.”

 

On page 18 GFE Programs: Divisions of Work. The Divisions of Work have been selected for this project and states, “Bidders may search for COBID-certified subcontractors”. Except for Divisions of work 91430 Concrete Work must be Self-Performed.

 

There doesn't appear to be any contradicting statements.

Where can the pre-bid attendee list be found?
Asked on 4/19/2023 10:14:37 AM
Answer:

This has been posted with the other bid documents on the bid page for this project. 

For Questions or Additional Information, Contact:

Name: Michael Phillips
Email: bidmail@BeavertonOregon.gov

Share: